PLC-5 → CONTROLLOGIXPHASED TRANSITIONCONVEYOR + SORTATION
The work
Our engineering background includes a phased migration involving approximately 20 processors, moving a conveyor and sortation system from PLC-5 to ControlLogix.
A separate three-rack migration included HMI work, operator training, and maintenance documentation, with startup carried out during a planned weekend changeover.
What carries into a new project: migration sequencing, interface awareness, cutover preparation, and a focus on the information the operations and maintenance teams need afterward.
These migration examples reflect engineering work completed before Honest Controls, LLC.